This single-stage operation was performed for the second time in the history of the Russian nuclear power industry.
On June 18, 2024, the dome was successfully lifted and installed at a single stage on the reactor building of Xudapu NPP power unit No. 4 (China) constructed with involvement of the Rosatom Engineering Division. This single-stage operation was performed for the second time in the history of the Russian nuclear power industry (it was performed for the first time at power unit No. 3 of the same plant in July 2023). The mature technology ensures a significant reduction in the time of the power unit construction.
“Unlike the traditional installation of the dome in two stages, the one-stage lifting technology significantly streamlines the process and reduces the time of this work. The 740-ton dome pre-assembled on the ground was lifted by crane on the reactor building. The reactor vessel is still to be installed at Unit 4, said Alexey Bannik, Atomstroyexport JSC Vice President for projects in China and prospective projects.
The polar crane was previously installed at the site, and this will help installing large-sized equipment after the installation and concreting works have been completed inside and outside the dome part of the reactor building.
For reference:
Xudapu NPP is a new project of cooperation between Russia and China in the field of nuclear energy, located in the city of Huludao (Liaoning Province). In 2019, a number of contracts were signed, including the General Contract for the construction of Units 3 and 4 of Xudapu NPP with VVER-1200 reactors, as well as a contract for nuclear fuel supply. In accordance with the contracts, the Russian party will design the nuclear island of the plant, supply the key equipment of the nuclear island for both units, provide designer’s supervision, installation supervision and adjustment supervision services for the equipment supplied.