Unit 2 of Novovoronezh Phase II successfully passed final tests and is ready for commissioning
On September 16, 2019 Unit 2 of Novovoronezh Phase II completed 15-day comprehensive trials of the equipment or so-called commissioning tests. The new innovative power unit ran fault-free at 100% capacity during the entire testing period. “We completed commissioning tests of the new power unit strictly on schedule. Results of the comprehensive trials speak about…